Construct Leave a Legacy Plaza

​​​​​​​

Project Delivery Method:
Project Budget:
Construction Duration:
Funding Source:
Design-Bid-Build
$1.3 million
2007-2007
Proposition S
 
Scope/Summary:
 
The project constructed a landscaped plaza, paved pathways, benches and lighting in an underdeveloped area between the Science & Technology building and the Automotive Technology Career Instructional building. These improvements provide access, connection, and enhance student safety.
 
 

Project Team:

  • Architect: Wimmer Yamada & Caughey
  • General Contractor: RSM2 Contractors, Inc.

 