College Service Center

​​​​​​​

Project Delivery Method:
Project Budget:
Construction Duration:
Funding Source:
​CM Multiprime
$5.9 million
2011-2012
Proposition N
 
 
Scope/Summary:
 
The College Service Center added approximately 8,400 gross square feet of new construction to the Miramar Campus. The one-story building houses the campus' Facilities Services Department. In addition to office and conference space, this facility centralized the much-needed equipment and storage on campus. 
 

Project Team:

  • Architect: gkkworks
  • Construction Manager: C.W. Driver
  • Civil Engineer: RBF Consulting
  • Structural Engineer: KPFF Consulting Engineers
  • Mechanical/Plumbing Engineer: MA Engineers
  • Electrical Engineer: Sparling/ILA Zammit
  • Landscape Architect: Wimmer Yamada and Caughey
  • Propositions S & N Program Manager: Gafcon, Inc.
  • Campus Project Manager: James Bray, Gafcon, Inc.
  • Project Manager: Joel Hermosillo, Gafcon, Inc.
  • Furniture, Fixture & Equipment (FF&E) Project Manager: Tricia Hendrickson, Gafcon, Inc.
     

 