Project Delivery Method:
Project Budget:
Construction Duration:
Funding Source:
​Design-Build
$16.3 million
2013 - 2014
Proposition N
 
 
Scope/Summary:
 
The Fire Technology & EMT Training Center consists of approximately 26,000 square feet of new construction and serves as a classroom and active training center for the District’s Fire Science and Emergency Medical Technician (EMT) programs. It includes lab support space, staging for equipment, and classrooms and offices. The outdoor training center includes a drill tower. The project is on track for a LEED Silver certification.

 

Project Team:

  • Architect: gkkworks
  • Design-Builder: Swinerton Builders
  • Structural Engineer: KPFF Consulting Engineers
  • Electrical Engineer: Sparling/ILA Zammit
  • Civil Engineer: RBF Consulting
  • Mechanical Engineer: MA Engineers
  • Landscape Architect: Wimmer Yamada & Caughey
  • Inspector of Record: Henderson Nugent, Cornerstone Quality Inspections
  • Propositions S & N Program Manager: Gafcon, Inc.
  • Campus Project Manager: Jim Bray, Gafcon, Inc.
  • Project Manager: Scott Ellis, URS Corp.
  • Furniture, Fixtures & Equipment (FF&E) Project Manager: Eloisa Raymundo, Gafcon, Inc.

 